With the MevaDec forms, early stripping is done by lowering the drop heads and removing the panels and beams which can then be used for the next pour. The props and drop heads remain in place until the slab has gained enough strength to be self-supporting.

Previously assembled conveniently on the ground, the AluFix panel gangs are crane-lifted to where they are needed for pouring, precisely positioned and then secured.

The formwork for the building’s outside walls is placed on the climbing scaffold KLK. Like the panel gangs, the climbing scaffold is crane-lifted from floor to floor.